We selected four Electricians and four Installation operatives to the project and organised a programme of training to be completed in the month prior to the contract start date. All operatives were subject to the training, regardless of whether they already had a valid certificate in this area. This ensured that the team were competent, trained in-line with National Highways Sector Scheme standards and their HERS (Highways Electrical Registration Scheme) ECS cards valid. As all operatives attended the training sessions together, they were also valuable team building exercises.
The project was to run in two Phases, the east side of the County was to be completed first using ‘Lantern A’ and on completion we were to move on to the west side of the County using ‘Lantern B’.
For logistical purposes it was agreed that we would use Qwest Services’ Depot in Winsford for Phase 1 of the project; all lanterns would be delivered and stored on site, our project manager would be based there and the teams would meet there each morning to collect their daily work packs and load up their vehicles. For Phase 2 we would move the operation to our Oakenholt depot as this is better placed for the areas in which we would be working.
We did encounter delays early on in this project due to supply chain issues, the lead time on the lanterns for Phase 1 of the project turned out to be much longer than anticipated when planning the programme of works and, due to the manufacturing capacity of the supplier, it was clear that we would run out of stock well before the next delivery. To avoid the project coming to a halt, our project manager worked closely with Qwest, the Council and the lantern suppliers and resolved to alter the programme of works. We arranged for two of the four teams to move over to the Oakenholt depot and begin installing the Phase 2 lanterns on the west side of the County, these lanterns were from a different manufacturer with a much shorter lead time. This slowed down the output on the Phase 1 installation enough so that they did not run out of stock before the next delivery.
We continued to monitor daily results and stock levels so that we were able to anticipate any further issues and propose a solution before it had an impact on the project. This flexible approach allowed work to continue seamlessly. In the planning stages we also considered the seasonal changes that would affect output, we knew that the teams would not be able to install as many lanterns in the winter months due to there being less daylight hours and potential bad weather which would make it unsafe to work. Wherever possible we countered this by adding an additional team to the project to ensure we stayed ahead of our weekly targets. In addition, we implemented staff incentives to motivate the operatives to ensure they met their weekly targets. Rewards varied from an early finish on a Friday to a team day out at the Races.
This approach, along with close monitoring of weekly progress and regular liaison with the key stakeholders enabled us to complete the project five months ahead of schedule.